Expansion update: parking garage renovation overview
24 May 2020
Learn the many improvements in store
By: Hannah Bauer, facilities development project consultant
What improvements can we expect?
- Emergency department parking: Convert first floor of garage to emergency department parking. Access will be through the ED driveway when complete.
- New entrance: Ramp from Capitol Street to the second floor of garage for nonemergency patient and employee parking.
- New exit: Move garage exit north on Capitol Street to ease congestion.
- Increase width of exit to make left turns out of the garage easier.
- Steel bracing around the outside of the structure.
How long will this take?
Construction begins June 1 with completion expected in September 2021.
What will happen to the garage during construction?
- Patients and employees can still park there during construction.
- Signs, flaggers, and barriers will help drivers safely navigate the garage.
- The parking garage is still the primary self-park option for patients coming to campus.
- Patients of Building C clinics and surgery patients may use the free valet service in the Building C garage on Winter Street.
- Emergency Department patients (and laboring mothers after 9 p.m.) may use the free valet service in the Oak Street turnaround.
Are we adding parking spaces?
No. We have sufficient parking to meet both current and future parking needs.
Reminder: if you have questions about your parking at Salem Hospital, please call 503-814-7275 or email parking@salemhealth.org.