Construction marches forward on the Building A expansion. The exterior of the building is nearly complete. The “parade of trades” continues as our craftspeople work their way through the building. Architectural finishes (paint, flooring, casework, wall protection and doors) are nearly complete on floor 4 and 5. Floors 6, 7 and 3 are receiving these finishes as the preceding floors are completed.
Transition planning for the move into A Expansion continues. We are refining the move plan and narrowing in on the specific “first patient” date and granular move schedule. Once operational departments finalize their timelines for transferring patients and equipment, programing technology, cleaning rooms between moves, etc., we will publish a complete move plan and communicate provider-specific impact.
As construction continues and we procure equipment and fixtures for A East, we continue to target April 2022 as the end of construction and July 2022 for first patient(s) being seen in the new units.